Permits and authorities
The paperwork for the town hall and ISC, at the start of the works, during them and at close-out.
Start
- F.13: start-of-works notice to the building-permit issuer (town hall)
- F.14: start-of-works notice to ISC/IJC
- Commencement order
- Proof of ISC fees (0.1% + 50% of 0.5%)
- Control programme by specialtySigned: beneficiary, designer, checker, contractor, site supervisor, RTE.
- Approval request for the hold-phase control programme (ISC form)
- Appointment decisions: RTE / site manager / site supervisor
- Investment identification board
- DTOE: technical documentation for organising execution (with the permit)
- Site-organisation permit / use of public landWhere applicable.
- Land-registry extract + cadastral plan (CATUC, ≤30 days)
- Prior notification / location endorsement (CATUC, small works)
During the works
Close-out
- F.15: completion notice to the town hall
- F.16: completion notice to ISC
- Annex 43: declaration of the real value of the works
- Final-value notification (from the town hall to ISC)
- Request for ISC fee certificate
- Request to appoint the ISC representative on the handover board
- Notice of start of the RTL board activity
- Energy performance certificate (buildings)
- Building-attestation certificate (cadastre / town hall)
- Refund request for ISC overpayments
- ISU fire-safety permit (after RTL)
- Entry in the National Constructions Register (CATUC, after handover)